Stops in the rafter bays. These are meant to create smaller compartments into which we'll be blowing in the cellulose. The smaller spaces help to avoid settling in a really long uninterrupted bay
Checking to see what sun is available when. The solar hot water panel will be placed at the upper right hand corner of the roof on the right. The key hours for solar activity are between 10:00 and 2:00. We'll be in good shape with this location
Like the first few raindrops before a shower, there is tangible evidence of our being very close to insulating. I've been spending time installing insulating foam around the windows, Joe has been installing fabric stops in the roof framing cavities, I have the cellulose blower on site, and our supplier is due to deliver 450 bales of cellulose on Thursday. Yes, 450.
We are busily checking off the last few items that need to be taken care of before we start sheathing the walls with Insulweb fabric, which is the first step in the insulating process. Its felt like we've been so close to ready for a while but there are seemingly always a few more things needing to be cleared up.
In other news, we have done some research and have now worked out the arrangements such that we'll be able to install a hot-water solar panel on the roof. This will supply hot water to our boiler so that it does not need to heat the otherwise cold water all the way from cold up to hot. With the collector in place there may be times when the boiler does not need to heat the water at all.
We are really excited about this development, thinking it would be something we'd plan for in the future but couldn't do now. Knowing we wanted to do it eventually, I installed the necessary copper lines so we wouldn't have to open up the walls later on. As I was doing this work it seemed like maybe we should just see what it would take to do it now, knowing it would save some headaches later on. One thing led to another and with the Federal credit it looks like its going to work out.
No comments:
Post a Comment