Today the gable-end wall on the north end of the house went up. There's a lot that needs to be done before lifting can happen, which we've been doing over the last couple of days. The rafters were shaped and installed, the sheathing was completed, and the furring strips installed. Additionally, we installed the frieze board and some of the clapboard siding at the peak, since this stuff will be hard to access once the wall is up.

Tomorrow we start on the south end.