Wednesday, April 7, 2010
Down in a hole
Still concentrating on preparations to take down the garage, I've spent the last two days digging a ten foot long trench that is three feet deep between our electric meter pedestal and the newly installed telephone pole. It was going fine until I hit the cementazoic layer--consisting mostly of super dense rock and clay that really was cement like. At one point I was considering giving up, but just about then started to break through to the next strata down and realized I'd be able to work through it.
Today I laid in the pipes for the new power service coming from the pole and got a start on the piping for the phone line as well. Felton has been coming up periodically to check on the progress and keep an eye on my work.
All this will allow us to remove the electrical panel and meter from the garage in anticipation of next week's work.
In the meantime Nancy has spent her evenings moving the firewood to its new location away from the garage and I'm slowly working through all the tools, bike parts, and random shoe-making machinery in the garage.
It'll all come together, but we've got a lot to do!
Monday, April 5, 2010
Switched out windows
Today Joe and I switched out the small triple-set second floor window for the larger pair. It went smoothly and we are quite happy with the result. Joe commented that if ever we want to sell the house, bring the potential buyer up to look out the window at the view and it'll seal the deal. I think he's right.
The new window not only opens up the upstairs room to the light and the view, it also helps to balance the exterior shapes a little. The window feels in proportion to the first floor windows.
We also pulled out, reframed and lowered the window you look out at the landing on the stairs. Now its about right for gazing out of as you pass by. It was about a foot too high.
Meanwhile, work on the garage is keeping us very busy. We continue to line up the pieces in order to bring the building down next week. This includes relocation of the power supply to the buildings, moving all our stuff out of the garage, moving the firewood stack next to the building, etc... there's a lot too it.
Thursday, April 1, 2010
Raidant tubing
The special stapler used to attach the radiant tubing. You have to contract the handle three times to insert one staple --which might seem cumbersome-- but it goes quicklyJoe came back yesterday morning after a break of about 2 1/2 months. Its good to have him back.
He and I tackled installing the remaining insulation in the basement yesterday and today set to work on installing the radiant tubing underneath the first floor. With any new project I always feel a little apprehension about getting up to speed and working out the inevitable questions or unknowns that arise. Starting on this project was no different, but after a little time to get going we worked out the routine and it went quite smoothly.
Tomorrow we'll finish up the radiant and if we have time switch out a two windows. One is a bigger window, the other is one that needs to be lowered. Its supposed to be a really nice day.
Oh yes, the power company came and dropped off a new telephone pole. They were going to install it, but the ground was so wet from the recent rain that the decided to come back early next week to actually put it up. So for the next few days we have a telephone pole in our driveway.
Tuesday, March 30, 2010
Hi Mary...
Recent events have prompted us to refocus our energy on taking down the garage sooner then we had originally planned. It means some scurrying now, but we're both excited at the prospect that the house will be able to stand on its own without the dubious presence of the garage right in front of it.
Given this new challenge, Nance and I have been working through the logistics of everything that needs to happen to actually have this thing torn down. Currently (no pun intended) the electric line from the pole goes to the meter and panel housed in the garage, as does the phone line. Relocating these requires timing, coordination, digging, and materials all be lined up and carefully ordered so that we are able to maintain service and make the switch safely, allowing for a large excavator to come in, knock down the building and then load it into dumpsters. Never mind that we have tons of stuff in there we need to sort through and then relocate to the basement. Its a big project, and it will delay focused progress on the house a bit, but it is ultimately part of getting the whole project done, so it really is just a reordering towards that end.
Friday, March 26, 2010
Friday Edition
There's some tidying-up to do, but I finished all the significant electrical work today. I'll have Felton come up again early next week and we'll do another walk-through to find any omissions or problems.
Tuesday, March 23, 2010
Window inspectors
The electrical work continued today, with a brief visit by two young window inspectors, along with their chauffeur. While carrying out their duties, they also checked out a couple of special spots that are excellent for kids to hide in while they play hide-n-seek with their uncle. As a thank-you for their services, they were sent home with some just-made maple syrup.
Labels:
electrical,
Liza,
Maia,
passive solar,
Solveig,
windows
Monday, March 22, 2010
Closing in on the electrical
Before moving on I'm going to go around and label everything so we know what is what and what is going where for what purpose. I've been labeling along the way, but not thoroughly, so I want to make sure we can understand everything once the sheetrock is covering the wires snaking through the walls.
The challenge is to anticipate and wire for intuitive light switching as you move through the house. I drew this all out in plan but have found myself mostly just doing it from feel in the actual house. Today I ran a circuit that allows us to turn on a light centrally located on the first floor from either entrance doorway or at the bottom of the stairs. A similar issue has been working out lighting for coming up the stair and going to bed. We've decided that we'll have a light over the bed that can be switched from either side of the bed and at the top of the stairs as you come up. The last photo shows the boxes in place for this as well as the blue light mounting box affixed to the rafter centered above.
I'm ready to get done with the electrical work and move on to completing the plumbing.