Today was Joe's first day on the job and it went great. We were getting ready for the concrete slab being poured sometime in the next few days. We had to build a retaining perimeter around the root cellar area and a thermal break at the doorway up to the bulkhead. We also laid down the plastic sheeting, then installed 2" rigid insulation. Once that was done we installed the pex tubing, by which we'll have radiant heat eventually running through the slab. It all went really well, but took way longer then I would have imagined. Hats off to Joe for sticking it out on a long day!